Question: At what stages do we have to pay you to build our new home? Answer:
We use the Housing Industry Associations (HIA) ‘Plain Language building contract’ which sets out the 6 stages for payment.
The 6 stages are:
Deposit (paid at contract signing – 5%)
Base (paid once the floor is down – either concrete slab or floor framing – 10%)
Frame (paid once the frame is erected – 15%)
Enclosed (paid once the house has been ‘locked up’ – 35%)
Fixing (paid once the plaster is up and the wet area’s have been tiled – 20%)
Practical Completion (paid when the house is complete – 15%).
Each of these stages are clearly identified within the building contract